Knowledge 2, Application 2, Analysis 2
Knowledge
Up to 2 marks for defining just in time (IIT) e.g.
- A manufacturing system where materials are delivered
immediately before they are needed (1) in order to minimise
costs (1)
OR
For giving two problems, e.g.
Application
Up to 2 marks for answers contextualised to Lotus Garments Co., e.g.
- The 11,800 employees need materials in order to make the
26,000,000 items of clothing annually (1)
Analysis
Up to 2 marks for reasons/causes/consequences for Lotus Garments
Co., e.g.
- If the employees run out of materials they cannot work and
would not be able to produce the garments needed to sell to
customers (1)
- If Lotus Garments Co. cannot rely on its local suppliers it may be
unable to meet the needs of its customers (1)
(6)