ConceptConceptDocsDocuments

CAIE A-Level Business 9.3.5 Operations planning

Practise using network diagrams and CPA to calculate float, project duration and judge planning decisions from operations data.

Syllabus
2026–2028
Course
Business 9609
Level
A2

Exam points

  • complete network diagram nodes using EST and LFT from activity data
  • calculate total float or minimum project duration from a critical path diagram
  • evaluate CPA as an operations planning tool, including its limits for managers

9.3.5—Operations planning question 1

[Maximum number: 16]

Refer to Table 1.1 and Fig. 1.1.

Question (a)

(a)

Calculate the minimum project duration.

[ 1 ]

Question (b)

(b)

Calculate the total float for activity D.

[ 3 ]

Question (c)

(c)

Evaluate whether critical path analysis (CPA) will ensure CP achieves its objective of minimising interruption to production.

[ 12 ]
All question bank results loaded