Practise operations strategy through ERP, lean production, CPA network diagrams, project timing and long-term case evaluation.
Evaluate the extent to which CA's operations strategy between 2019 and 2024 led to the failure of the city Z branch.
AO1 Knowledge and understanding
Knowledge □ (max 1 mark) can be awarded for any relevant business knowledge about operations, including:
- The transformation process
- Efficiency, effectiveness, productivity and sustainability
- Capital intensive and labour intensive operations
- Job, batch, flow and mass customisation
- Managing inventory, including JIT
- Capacity utilisation
- Outsourcing
- Location
- Economies and diseconomies of scale
- Quality management, including benchmarking
- The influence of human, marketing and finance resource availability on operations decisions
- The changing role of Information Technology (IT) and Artificial Intelligence (AI)
- The need for flexibility with regard to volume, delivery time and specification
- Process innovation: changing current processes or adopting new ways of producing products or delivering services
- Location
- Internal and external economies and diseconomies of scale
- Quality management
- Benchmarking
- Improving flexibility and innovation
- Enterprise resource planning (ERP)
- Lean production
- Operations planning, including critical path analysis.
Award [DEV] for any explanation of relevant business knowledge, up to a max of 2 marks.
1 K for identification and 1 DEV for a point of explanation
1 K for identification and 2 DEVs for two points of explanation
1
AO2 Application
Application [m≪] (max 2 marks) can be awarded for applying operations/operations strategy to CA between 2019 and 2024 CA's operations decisions, including:
- CA is Nala's first job after university, only experience before being made Operations Manager was as a cleaner for CA.
- Planning opening of the new city Z branch, including:
- The use of critical path analysis
- 13 weeks to plan and open the branch (assuming no delays)
- Float available on activities C, D, F, G and H
- Critical path = A, B, E and J
- No built-in time to respond to research results
- Lean production methods introduced by Nala in 2021, including:
- Kaizen (continuous improvement) introduced throughout city Z branch
- All cleaners are placed in a quality circle, including one manager and eight cleaners in each team
- A target to ethically recycle 90% of customers waste
- Just in time re-ordering of cleaning materials
- CA's new AI system introduced in 2022, including:
- Majority of customer services operatives made redundant
- Chatbot system to interact with customers
- Book appointments, answer customer queries and take complaints
- Poor customer/media reaction
- Comparison between the operations of the city Z branch and the city A branch of CA in 2023, including:
- City Z branch has lower revenue than city A
- City Z branch has sightly improved revenue between 2021 and 2023 ( 2% increase)
- City A branch has 10% improved revenue between 2021 and 2023
- City Z branch has improved revenue, same number of cleaners whereas city A branch has increased cleaners
- City Z branch has a loss of $0.1 m in 2023, compared to an increased profit for city A branch.
- City Z branch has increased direct costs, despite introduction of lean production methods
- Rate of inventory turnover has increased in city Z branch (suggesting improvement) but may not have added to cost savings.
1
AO3 Analysis
Analysis is likely to be based on how operations may have affected CA's decision making ( △1 and A2 and △3 ) between 2019 and 2024, including:
- Nala's inexperience - poor decision making - too much responsibility - may have been integral to the failure of city Z branch - particularly important since city A branch has increased profitability.
- Did the city Z branch open too quickly? - Is 13 weeks long enough to plan such a large investment? - poor implementation of decisions.
- Critical path analysis is a useful theoretical tool, but does it have enough practical value when Nala and the business are new to the city? - increased costs - reduced profit.
- Built-in float may suggest inefficiency - Was the rent paid for too long before opening? - increased costs - reduced profitability.
- Employee recruitment in city Z had float - increased costs - reduced profit.
- However, CPA may have led to a more efficient opening - reduced costs - increased profit.
- No float between advertising and bookings - efficient.
- CPA allowed Nala to focus on what areas are most important - increased efficiency.
- Kaizen may have allowed more creative ideas to come from every area of the business - lower costs - however also detracts from the primary task of the cleaners (and other employees) - increased costs.
- Likewise, quality circles may detract from cleaning - may theoretically (academically) increase value of workforce but could lead to wasted time not focused on primary tasks like cleaning - increased costs. Also there may be problems of bringing mainly part-time employees together for meeting - may incur additional costs for wages. Also, attendance and contributions might depend on whether workers are paid for attending or not - employees may feel resentful and become demotivated - deceased productivity.
- Ethical recycling of customer waste may provide a USP to CA in city Z - however only if customers value this in the market.
- Just in time ordering may decrease costs of holding inventory - however it may lead to wasted time without necessary supplies.
- Chatbot system may lead to reduced indirect costs (less customer service employees needed) - however seems to have irritated customers and may lead to losing established customers going to other firms.
Link between figures in Appendix 4 and operations decisions.
1
AO4 Evaluation
Evaluation (N1 and N2 and N3 ) including:
Evaluation will largely depend on the points raised in the analysis.
- A judgement over the extent to which operational decisions between 2019 and 2024 led to the failure of CA's city Z branch.
- Discussion over the contribution of the separate and combined decisions on the eventual failure of the city Z branch,
- The extent to which the decisions alone led to the failure of the city Z branch.
- Other likely influences on the failure of the city Z branch, such as the state of the economy in city Z, human resource management of the cleaners and indirect staff, Nala's personality, unrealistic expectations of the board of directors of CA, marketing of CA, especially for the city Z branch, the financing given to help the city Z branch become successful etc.
- The extent to which the failure of the city Z branch could be attributed to the operational decisions alone.
- The extent to which CA itself was deemed successful (city A branch).
Accept all valid responses.
1
Exemplars for awarding evaluation:
L2 □
including: (developed supporting evidence)

including: (developed supporting evidence with context)
No credit &
L1 N1 including:
(limited
supporting
evidence)
L
s
The operations
strategy did lead
to the failure of
the city Z branch.
The operations
strategy did lead to
the failure of the city
Z branch because it
was poorly
implemented.
The
the
b
im
m
m
a
\end{tabular}
The operations strategy did lead to
the failure of the city Z branch
because it was poorly
implemented. This meant that the
money spent on the lean
production methods was wasted
and it could have been spent on
something else.
The operations strategy did lead to
the failure of the city Z branch
because it was poorly implemented
by Nala who was inexperienced.
This meant that the money spent on
the lean production methods was
wasted and it could have been
spent on something else.
The reason the
city Z branch
failed was due to
the marketing.
The reason the city
Z branch failed was
due to the
marketing not the
operations.
The reason the city Z branch failed
was due to the marketing not the
operations. This is because they
did not do enough market research
to back up their strategic
decisions.
The reason the city Z branch failed
was due to the marketing not the
operations. This is because they did
not do enough market research to
back up their strategic decisions,
such as research whether
customers want 90\% of their waste
recycled.
Evaluate whether introducing lean production will be sufficient to achieve CQ's operational objectives.
3(c)
Indicative content
Responses may include:
AO1 Knowledge and understanding
Limited knowledge K will be demonstrated through knowledge of lean production or knowledge of impact on operational objectives.
Developed knowledge K+K will be demonstrated through knowledge of lean production and knowledge of impact on operational objectives.
- Definition of lean production: reducing all forms of waste.
- Lean production techniques:
- TQM
- Quality circles
- Cell production
- JIT
- Kaizen
- Simultaneous engineering.
- Need for capital investment such as ERP or flexible machinery.
- Knowledge of relevant ratios such as inventory turnover.
AO2 Application
Limited application, APP applies knowledge to CQ once.
Developed application, APP + APP applies knowledge to CQ twice.
- Inventory turnover of 3.08 means that inventory is currently kept for 119 days on average. Objective is to increase inventory turnover to 5 times.
- Need to hold bamboo material for production and finished shoes to meet fluctuations in demand.
- 5% of output is defective - in six months =6000 units. Objective is to cut this by 50%.
- CQ has only just taken over the factory. Objective to increase production to full capacity within eight months and reduce workforce size.
- The shoe manufacturer had been unprofitable when CQ took it over.
- Unions have agreed to changes in working practices.
3(c)
AO3 Analysis
Limited analysis AN - candidate shows one link in the chain of analysis.
Developed analysis L2AN - candidate shows two or more links in the chain of analysis.
- By reducing all forms of waste CQ will be more efficient, and this will reduce unit cost of production AN making CQ more competitive. L2 AN
- Lean production includes TQM and quality circles. Giving workers responsibility for quality may increase motivation resulting in a reduction in defective output, AN improve quality and productivity, making CQ more competitive. L2 AN
- Lean production includes JIT manufacturing. Aim to hold zero inventory which will increase inventory turnover AN resulting in less inventory holding costs. L2 AN
- Training of employees will be required thus increasing costs of CQ AN but this could increase motivation of employees resulting in higher productivity. L2 AN
- Lean production aims to use less of everything and therefore may enable production to be maintained whilst reducing the size of the labour force AN and therefore reduce unit costs. L2 AN
- Lean production by building relationship with suppliers could eliminate the supply chain failures AN thus reducing the high levels of inventory previously needed. L2/AN
- Use of JIT may result in CQ running out of inventory and therefore lead to a loss of sales. AN
AO4 Evaluation
Limited evaluation EvAL - limited supported judgement and/or a weak attempt at evaluative comment.
Developed evaluation L2 EvaL - supported judgement and/or reasonable evaluative comment.
Developed evaluation in context L3 | Eval - supported judgement in context and/or reasonable evaluative comment in context.
- Elements that the evaluation/judgement might depend on:
- Effectiveness will depend on supplier relationships and reliability of receiving supplies when needed. Supply chain with bamboo coming from the US may make JIT production difficult to implement due to long lead times.
- Can CQ predict demand accurately? JIT risks lost customers if demand is underestimated.
- Is inventory turnover high or low compared to competitors?
- Was part of the problem that workers are unfamiliar with the production methods for the bamboo shoes after the takeover?
- Cost of the investment and current financial situation of CQ such as its high gearing.
PUBLISHED
3(c)
- Significance of other factors that may also impact success of LP:
- Existing factory, workers may have an ingrained culture to overcome.
- Evaluation of alternative approaches to achieving objectives such as investment in capital equipment or increased marketing expenditure to increase sales and inventory turnover.
- Supported overall judgement about introduction of LP.
- Accept all valid responses.
Refer to Table 1.1 and Fig. 1.1.
Calculate the minimum project duration.
Refer to Table 1.1 and Fig. 1.1. Calculate the minimum project duration.
Responses may include:
CP = 13 (weeks) (1)
Calculate the total float for activity D.
Refer to Table 1.1 and Fig. 1.1. Calculate the total float for activity D.
Responses may include:
Total float activity is time an activity can be delayed without delaying overall project duration.
LFT - duration - EST (1)
10-1 - 4 (2)
Total Float =5 (weeks) (3)
Accept all valid responses.
Evaluate whether critical path analysis (CPA) will ensure CP achieves its objective of minimising interruption to production.

3
AO1 Knowledge and understanding 2 marks
AO2 Application 2 marks
AO3 Analysis 2 marks
AO4 Evaluation 6 marks
5-6 marks
Developed evaluation in context
- A developed judgement/conclusion is made in the business context.
- Developed evaluative comments which balance some key arguments in the business context.
2
2 marks
Developed knowledge of relevant key term(s) and/or factor(s) is used to answer the question.
2 marks
Developed application of relevant point(s) to the business context.
2 marks
Developed analysis that identifies
connections between
causes, impacts and/or
consequences.
3-4 marks
Developed evaluation
- A developed judgement/conclusion is made.
- Developed evaluative comments which balance some key arguments.
1
1 mark
Limited knowledge of relevant key term(s) and/or factor(s) is used to answer the question.
1 mark
Limited application of relevant point(s) to the business context.
1 mark
Limited analysis that identifies
connections between
causes, impacts and/or
consequences.
1-2 marks
Limited evaluation
- A judgement/conclusion is made with limited supporting comment/evidence.
- An attempt is made to balance the arguments.
0
0 marks
No creditable response.
0 marks
No creditable response.
0 marks
No creditable response.
0 marks
No creditable response.
3(c)
Indicative content
Responses may include:
AO1 Knowledge and understanding
Limited knowledge K will be demonstrated through knowledge of critical path analysis (CPA) or benefits of CPA
Developed knowledge K+K+ will be demonstrated through knowledge of critical path analysis (CPA) and benefits/limitations of CPA
- Understanding of CPA - network diagram, critical path, floats, minimum duration.
- Benefits of CPA: knowing minimum project time, start times for activities, progress monitoring, assessing significance of delays and if necessary, corrective actions.
- Limitations of CPA: analysis only as good as input data, planning costs, does not ensure effective management.
AO2 Application
Limited application, △APP applies knowledge to CP once.
Developed application, APP +APP applies knowledge to CP twice.
Max one APP for application for the first impact of technological change and max one APP for application for the second impact of technological change.
- Importance of continuous supply to retailers.
- Contractor produced CPA.
- Contract based on accuracy and reliability of CPA.
3(c)
AO3 Analysis
Limited analysis AN - candidate shows one link in the chain of analysis.
Developed analysis L2|AN - candidate shows two or more links in the chain of analysis OR offers a two-sided analysis.
- Development of knowledge and application points about usefulness of CPA to CP.
- CPA is quantitative as it allocates timings to activities, so can help with planning and monitoring to ensure project does not over-run. AN
- Contractor may have produced CPA and contract terms in order to get the contract. This may mean contract takes longer AN, which will lead to delays and dissatisfied customers. L2 AN
- CPA enables CP to determine non-production time and prepare, by building up inventory, before work starts. This will enable sales to proceed as normal AN and avoid potential of unmet orders and decreased sales and profit. L2 AN
- Enables monitoring critical activities, such as E (delivery of components) and allows CP to take action if a delay is threatened to ensure project is completed on time AN, minimising production interruptions.
AO4 Evaluation
Limited evaluation EvAL - limited supported judgement and/or a weak attempt at evaluative comment.
Developed evaluation L2 EvaL - supported judgement and/or reasonable evaluative comment.
Developed evaluation in context L3 EvAL - supported judgement in context and/or reasonable evaluative comment in context.
- Either conclusion is valid, as long as it is justified.
- CP has contract provision that CPA for the external use paint production line is accurate and reliable so more likely that it is, as the contractor will not want to pay penalty fees.
- CP experienced in paint production, rather than production line installation, so not likely to know accuracy of CPA.
- An accurate CPA will be very important for enabling continuous supply of external paints, so customers are not disappointed.
- CPA only as good as data and the skills of the person who prepared it. Some question about its accuracy so CP wise not to rely solely on its results, especially as the price is low and the contractor produced it.
- Other information is also important, such as staff training. The CPA does not allow for this.
- Work progress has to match the CPA plan, so CP would be wise to maintain constant check on progress before and after work starts.
Accept all valid responses.