Edexcel IAL Mathematics D1.4.4 total float
Practise total float and scheduling by using event times, cascade charts and worker limits to justify project decisions.
- Syllabus
- First assessment 2019
- Course
- Mathematics YMA01
- Level
- AS
Practise total float and scheduling by using event times, cascade charts and worker limits to justify project decisions.




Diagram 1

Diagram 2

Figure 2
[The sum of the durations of all the activities is 133 days]
A project is modelled by the activity network shown in Figure 2. The activities are represented by the arcs. The number in brackets on each arc gives the time, in days, to complete the activity. Each activity requires one worker. The project is to be completed in the shortest possible time.
Calculate the total float for activity J. You must make the numbers you use in your calculation clear.
Float on J=35-22-5=8
B1ft (1)
Calculate a lower bound for the number of workers needed to complete the project in the minimum time. You must show your working.
Diagram 2 in the answer book shows a partly completed scheduling diagram for this project.
Lower bound is 43133=3.0930…=4
B1 (1)
Complete the scheduling diagram, using the minimum number of workers, so that the project is completed in the minimum time.
e.g.

M1
A1
A1
A1