3.3.3 - Decision-making techniques
- Syllabus
- 2017
- Topic
- 3.3.3
- Level
- A2
A moving average smooths short-term fluctuations so the underlying direction of a time series is easier to see. Use the number of consecutive observations named in the question and keep the original unit.
| Required average | Calculation | Position |
|---|---|---|
| three-period | add three consecutive values and divide by 3 | place against the middle period |
| four-quarter | add four consecutive quarterly values and divide by 4 | lies between the two middle quarters; average adjacent four-quarter averages if a centred quarterly trend is required |
For annual percentages 65, 66 and 72, the three-period moving average is (65 + 66 + 72) / 3 = 67.67%. Then move the window forward one period and repeat; do not reuse a three-year total as though it were a single observation.
Compare successive moving averages: a rising series indicates an upward trend after irregular variation has been smoothed. The calculation describes the historical trend; it does not by itself explain why sales changed.
A three-period moving average is not three separate averages, and a four-quarter average may need centring before it is matched to a particular quarter. Never mix totals, percentages or currencies without checking the data unit.
A scatter graph plots paired observations. The direction and closeness of the points show correlation; a line of best fit represents the general relationship and can be extended to estimate a future value.
| Evidence in the graph | Interpretation |
|---|---|
| points rise from left to right | positive correlation |
| points fall from left to right | negative correlation |
| points cluster closely around the line | stronger relationship and usually a more stable estimate |
| points are widely dispersed or contain outliers | weaker relationship and greater forecast uncertainty |
Identify the input value, move to the line of best fit, then read the estimated output from the other axis. Interpolation stays within observed data; extrapolation extends beyond it and assumes the past relationship continues.
If the fitted line links advertising expenditure to sales, a future advertising budget can be mapped to an estimated sales figure. State it as an estimate and use the axis scale and units precisely.
Correlation does not prove that one variable caused the other. Extrapolation is less secure than interpolation because the forecast lies outside the observed range, and a line should represent the overall pattern rather than join every point.
Quantitative forecasting converts historical data into a numerical trend, but its apparent precision depends on the relevance, quality and stability of the data and assumptions.
| Limitation | Why the forecast may fail | Context test |
|---|---|---|
| historical dependence | consumer tastes, technology or competition may change | is the market stable enough for the old pattern to continue? |
| exceptional events | shocks or one-off promotions distort the series | should an outlier be adjusted or explained? |
| data quality and horizon | short, inaccurate or unrepresentative records create a weak trend | how many comparable periods are available? |
| model simplification | seasonality or causal factors may be omitted | does the technique capture the pattern in this business? |
| quantitative focus | staff knowledge, brand reaction or regulation is not measured | what qualitative evidence should accompany the forecast? |
A forecast is more useful when past forecasts were accurate, the data are recent and comparable, and the business tests alternative assumptions. It is less useful in a rapidly changing market or over a long extrapolation distance.
A small past forecast error does not guarantee future accuracy, and one inaccurate output does not make all quantitative forecasting useless. Judge reliability from the source data, assumptions, horizon and business context.
The simple payback period is the time taken for forecast net cash inflows to recover the initial investment. A shorter payback normally means the cash is recovered sooner and is exposed to uncertainty for less time.
| Cash-flow pattern | Method |
|---|---|
| equal annual net cash flow | payback = initial investment / annual net cash flow |
| unequal annual net cash flows | accumulate each year's net cash flow until the outlay is recovered; fraction of final year = amount still unrecovered / final year's net cash flow |
An investment of £120,000 returning £30,000 each year has a payback of £120,000 / £30,000 = 4 years. If £15,000 remains after year 3 and year 4 brings £30,000, payback is 3 + 15,000/30,000 = 3.5 years, or about 3 years 6 months.
Compare the result with the firm's target payback and with alternatives calculated on the same basis. Faster recovery can support liquidity, but does not establish which project creates the most total return.
Use net cash flow, not accounting profit or sales revenue. Simple payback ignores cash flows after recovery and the time value of money, so the shortest payback is not automatically the best investment.
Average accounting rate of return (ARR) compares the average annual profit generated by a project with its initial investment and expresses the result as a percentage.
ARR (%) = (average annual profit / initial investment) × 100, where average annual profit = total forecast profit over the project's life / number of years.
If total forecast profit is £287,550 over 6 years and the initial investment is £150,000, average annual profit is £47,925 and ARR = (£47,925 / £150,000) × 100 = 31.95%.
A higher ARR is normally preferred and should be compared with the firm's required return or other projects. The percentage helps compare projects of different scale, provided profit definitions and time periods are consistent.
ARR uses accounting profit rather than cash flow and does not show when within the project life the profit occurs. Do not divide total profit directly by the investment without first finding average annual profit.
Discounted cash flow recognises that money received later is worth less than money received now. Net present value (NPV) compares the present value of forecast net cash flows with the initial cost.
| Step | Calculation |
|---|---|
| 1 | discounted cash flow for each year = net cash flow × supplied discount factor |
| 2 | total the discounted cash flows |
| 3 | NPV = total discounted cash flows − initial investment |
If the discounted cash inflows total £21,635 and the machine costs £10,000 now, NPV = £21,635 − £10,000 = £11,635. A positive NPV means the forecast return exceeds the return represented by the chosen discount rate.
With comparable risk and assumptions, a higher positive NPV is financially more attractive; a negative NPV fails to meet the chosen discount rate. The result remains a forecast, not cash already earned.
The discount factor is applied to each future net cash flow, not to the initial outlay at time zero. This syllabus objective is NPV only: do not widen it to internal rate of return.
Investment appraisal figures are useful only when their meaning is matched to the decision. Payback focuses on recovery time, ARR on average profit relative to investment, and NPV on value after discounting future cash flows.
| Result | More attractive signal | Relevant benchmark |
|---|---|---|
| payback | shorter recovery period | maximum acceptable payback and liquidity need |
| ARR | higher percentage return | target ARR or return from alternatives |
| NPV | larger positive value | zero, required discount rate and comparable projects |
First confirm that figures use comparable time periods, costs and assumptions. Then connect the result to the firm's objective: a cash-constrained firm may value rapid payback, while a long-term investor may give greater weight to NPV.
A method can rank alternatives differently because it measures a different feature. Use the figures together with project scale, risk, finance and strategic fit rather than searching for one universally decisive number.
A positive result is not automatically best: 20% ARR needs a benchmark, a three-year payback needs a target, and positive NPV alternatives still differ in scale and risk. Interpretation must state what is being compared.
All investment appraisal methods simplify an uncertain future. Their usefulness depends on the accuracy of cash-flow or profit forecasts and on whether the technique matches the firm's objective.
| Technique | Important limitation |
|---|---|
| simple payback | ignores returns after payback and the time value of money |
| ARR | uses accounting profit and ignores the timing of profits |
| NPV | depends on estimated cash flows and the chosen discount rate |
| all methods | omit or reduce qualitative factors such as strategic fit, environmental impact, employee capability and brand effect |
Forecast error matters more for a large, long-lived or irreversible project. Sensitivity testing, comparison of methods, experienced estimates and qualitative analysis can improve the decision, but cannot remove uncertainty.
A calculated figure is not objective truth. A technically weaker method may still provide useful information—for example, payback for a liquidity-constrained firm—so evaluate the method against the decision rather than dismissing it in isolation.
A decision tree displays alternative choices and uncertain outcomes in a sequence. It makes the assumptions visible so managers can compare options consistently.
| Feature | Meaning |
|---|---|
| square decision node | point where the business chooses between options |
| branch from a decision node | one available course of action |
| circle chance node | point where an uncertain outcome occurs |
| branch from a chance node | outcome labelled with its probability and financial result |
| endpoint | final outcome from that route |
Draw choices from left to right. After each choice, add its possible outcomes, label probabilities and returns, and check that mutually exclusive probabilities at each chance node sum to 1. Put any initial cost on the relevant option.
Work back from right to left after calculating expected values. The tree helps compare alternatives, but the final recommendation should also test whether the inputs and omitted qualitative factors are credible.
Decision nodes and chance nodes are not interchangeable, and probabilities from separate chance nodes do not need to sum together. The tree is a model of specified alternatives, not proof that every possible outcome has been included.
Expected monetary value (EMV) is the probability-weighted average financial outcome. Calculate it at each chance node, then deduct the initial cost of the option to compare net expected values.
EMV at a chance node = Σ(probability × financial outcome). Net expected value of an option = EMV − initial investment cost.
Option A has a 0.4 probability of £7m and a 0.6 probability of −£1m: EMV = (0.4 × £7m) + (0.6 × −£1m) = £2.2m. If a separate initial cost exists, subtract it once after weighting the outcomes.
On the quantitative evidence alone, choose the option with the highest net expected value. Then consider the range of outcomes, affordability, time, strategic fit and reliability of the probabilities before making a recommendation.
Do not select the single largest possible payoff or multiply costs twice. EMV is a long-run probability-weighted estimate; the business will experience one outcome, not necessarily the average value.
A decision tree structures uncertainty and makes alternatives comparable, but its numerical result is only as credible as the estimated probabilities, returns and choices included.
| Limitation | Effect on the decision | Possible response |
|---|---|---|
| subjective probabilities | small changes can reverse the preferred option | use research, experience and sensitivity testing |
| estimated financial outcomes | EMV can give false confidence | show ranges and update forecasts |
| omitted qualitative factors | culture, brand, ethics or capability may favour another option | combine the tree with qualitative analysis |
| simplified choices | interacting or sequential decisions may be excluded | revise the tree as information changes |
| risk attitude and cash limits | highest EMV may expose the firm to an unaffordable loss | examine downside and finance, not EMV alone |
The technique is strongest for clearly defined alternatives with defensible probabilities and comparable monetary consequences. It is weaker for novel, long-term decisions dominated by human response or external shocks.
Decision trees organise risk; they do not reduce the probability of an adverse outcome. A visual diagram and a precise EMV should not be mistaken for certainty.
Critical path analysis (CPA) represents a project as linked activities with durations and dependencies. Its purpose is to identify the minimum completion time and the activities that cannot be delayed without delaying the whole project.
| Information from CPA | Management use |
|---|---|
| activity sequence and dependencies | schedule work in a feasible order |
| critical path | prioritise monitoring and resources where delay affects completion |
| project duration | plan launch dates, closures, contracts and budgets |
| float on non-critical activities | move limited labour or equipment without extending the project, within available float |
CPA can coordinate a building project, factory change or marketing launch. Managers can see where a delayed critical activity will affect every dependent activity and where resources might be reallocated.
CPA seeks the shortest feasible project duration under the stated durations and dependencies; it does not by itself make every activity faster, guarantee quality or guarantee commercial success.
A project network links activities in dependency order. Complete a semi-finished network, calculate timings through it, and identify the route whose activities determine the minimum project duration.
| Pass | Rule |
|---|---|
| forward | move left to right; an event can start only after all incoming activities finish, so take the largest incoming finish time |
| backward | move right to left from the project finish; where routes split, take the smallest allowable time |
| identify | activities with zero total float form the critical path; their durations sum to the project duration |
A delay to a critical activity delays the project unless time is recovered elsewhere on the critical path. A non-critical activity may be delayed only up to its available float before it becomes critical or affects a successor.
The critical path is the longest time route, not the route with the most activities. This syllabus requires completing and interpreting simple or semi-complete networks, not constructing a full network from scratch.
Earliest start time (EST) is found by a forward pass; latest finish time (LFT) is found by a backward pass. Together they show how much an activity can slip without delaying the project.
| Quantity | Calculation rule |
|---|---|
| EST at an event | largest of each predecessor's EST + activity duration |
| LFT at an event | smallest of each successor's LFT − activity duration |
| total float for activity i→j | LFT at j − duration of i→j − EST at i |
If an activity starts from an event with EST 8, lasts 4 weeks and ends at an event with LFT 16, total float = 16 − 4 − 8 = 4 weeks. Zero float indicates a critical activity.
The start event normally has EST 0. At the final event, EST and LFT equal the minimum project duration. At a merge use the largest forward value; at a split use the smallest backward value.
Float belongs to a particular activity and dependency position, not automatically to an entire route. Do not use the smallest incoming value on the forward pass or the largest outgoing value on the backward pass.
CPA is a planning model. Errors in activity duration, dependencies or resource assumptions can make the calculated completion date and float misleading.
| Limitation | Consequence |
|---|---|
| uncertain duration estimates | a critical activity may overrun and delay all successors |
| activities do not start exactly on time | contractors, materials or approvals create hidden delay |
| resource assumptions | simultaneous activities may compete for the same people or equipment |
| changing dependencies | rework or unexpected events make the original network obsolete |
| qualitative omission | weather, quality, safety and staff capability are not captured by timings alone |
CPA is more useful for familiar, divisible projects with reliable estimates and active monitoring. Managers should update the network, build contingencies and combine timing information with cost, quality and risk controls.
Zero float does not mean an activity will be completed on time, and positive float is not spare time that can always be consumed without consequence. It is conditional on the rest of the network remaining as planned.
Contribution is the amount remaining after variable costs are deducted from sales revenue. It first contributes toward fixed costs; only contribution above total fixed costs becomes profit.
| Measure | Relationship |
|---|---|
| contribution per unit | selling price per unit − variable cost per unit |
| total contribution | total revenue − total variable cost, or contribution per unit × units sold |
| profit | total contribution − total fixed costs |
Contribution isolates the extra amount generated by a product or decision before fixed cost allocation. This helps analyse product mix, pricing, special orders and whether limited capacity should be used for one option rather than another.
Contribution is not profit because fixed costs still need to be paid. A product with positive contribution can reduce an overall loss, while a product with negative contribution makes the position worse for every additional unit.
Contribution must be calculated with consistent units. Find per-unit contribution for a single product decision or total contribution when assessing the overall result.
Contribution per unit = selling price per unit − variable cost per unit. Total contribution = contribution per unit × output. Profit = total contribution − fixed costs.
If a product sells for £50, variable cost is £32 and 4,000 units are sold, contribution per unit is £18 and total contribution is £72,000. With fixed costs of £55,000, profit is £17,000.
Higher total contribution provides more toward fixed costs and profit, but output, capacity use and any additional fixed cost must be included. When a scarce resource constrains output, compare contribution per unit of that limiting factor.
Do not subtract fixed cost when calculating contribution per unit, and do not compare per-unit contribution with total contribution. A high contribution per unit can still yield lower total contribution if too few units are sold.
Contribution analysis asks how a decision changes revenue and variable cost, then whether the resulting contribution is sufficient given fixed costs, capacity and alternatives.
| Decision | Contribution test | Further condition |
|---|---|---|
| accept a special order | additional revenue exceeds additional variable cost | spare capacity, price precedent and customer effects |
| choose a product mix | maximise contribution from constrained capacity | compare contribution per unit of the limiting factor |
| discontinue a product | identify contribution that would be lost | remove only fixed costs that are genuinely avoidable |
| make or buy | compare relevant incremental costs and contribution effects | quality, supplier reliability and use of released capacity |
A special order at £28 with variable cost £22 adds £6 contribution per unit if spare capacity exists. It may help cover fixed costs, but displacement of regular sales or an added fixed setup cost could reverse the decision.
Use contribution for the incremental financial effect, then test demand, capacity, opportunity cost, quality and strategy. The recommendation should state which assumptions make the decision worthwhile.
Allocated fixed cost is not automatically avoidable, and positive unit contribution is not automatic approval. A decision can reduce total contribution by displacing a more valuable use of scarce capacity.