Question 4
Question 4(a)
(a)
Using Figure 1.1:
[ 4 ]
Question 4(a)(i)
(i)
calculate the total float for activity C
[ 3 ]
Question 4(a)(ii)
(ii)
identify the minimum project duration.
[ 1 ]
Question 4(b)
(b)
Evaluate the importance of Critical Path Analysis (CPA) to the success of the hard rock mine.
[ 12 ]