6.1.10 (HL)—Gantt chart
- Syllabus
- First assessment 2024
- Objective
- 6.1.10
- Level
- HL
A Gantt chart places project tasks on a timeline, showing duration, overlap, milestones and progress.
It supports coordination but does not by itself show task dependency or resource conflicts well.
Check sequencing, owners and slack, then update actual progress.
A website launch shows design before testing, with a milestone for approval.
A bar on a chart is not a completed outcome.